Gantry Crane Track at the Port of Açú

Project Details

Start Date 2014
End Date 2014
ClientAnglo Ferrous Minas 
CountryBrazil
LocationSão João da Barra 
Project Status Completed

Description

The project consisted of the installation of three crane tracks with a total length of 2800 m, with an 8 m gauge and laid over a ballast bed. In order to support the rails, this system relies on concrete blocks embedded in the ballast.