Modernization of the line between Thenia and Oued Aissi

Project Details

Start Date January 2009
End Date 
ClientANESRIF – Agence Nationale d’Etudes et de Suivi de la Réalisation des Investissements Ferroviaires
CountryAlgeria
LocationThenia – Oued Aissi 
Project Status Underway

Project Objectives

1. Design and Construction of 56 km of Track. 2. Design and Installation of 65 km of Overhead Line. 3. Design and Construction of 2 Substations.

Description

The project consisted of the construction of 56 km of Track and installation of 65 km of Overhead Line, between Thenia and Oued Aissi. The Project also included the preparation of the final design of the track and electrification system, as well as the design and installation of both substations.