Project Details

Start Date January 2009
End Date 
ClientANESRIF – Agence Nationale d’Etudes et de Suivi de la Réalisation des Investissements Ferroviaires
CountryAlgeria
LocationThenia – Oued Aissi 
Project Status Underway

Project Objectives

1. Design and Construction of 56 km of Track. 2. Design and Installation of 65 km of Overhead Line. 3. Design and Construction of 2 Substations.

Description

The project consisted of the construction of 56 km of Track and installation of 65 km of Overhead Line, between Thenia and Oued Aissi. The Project also included the preparation of the final design of the track and electrification system, as well as the design and installation of both substations.

Cofinanciamento
Privacy Overview
SOMAFEL

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful.

Strictly Necessary Cookies

Strictly Necessary Cookie should be enabled at all times so that we can save your preferences for cookie settings.

Analytics

This website uses Google Analytics to collect anonymous information such as the number of visitors to the site, and the most popular pages.

Keeping this cookie enabled helps us to improve our website.