Track refurbishment between El Gourzi and Touggourt

Project Details

Start Date May 2007 
End Date June 2011
ClientANESRIF – Agence Nationale d’Etudes et de Suivi de la Réalisation des Investissements Ferroviaires
CountryAlgeria
LocationEl Gourzi – Touggourt 
Project Status Completed

Project Objectives 

Refurbishment of 240 km of Track

Description

The Project consisted of the Study, Design and Performance of the track refurbishment works between El Gourzi and Tougourt along 240 km. As part of this project, a sleeper factory was built and the related construction works were carried out.