| Start Date | May 2007 |
| End Date | June 2011 |
| Client | ANESRIF – Agence Nationale d’Etudes et de Suivi de la Réalisation des Investissements Ferroviaires |
| Country | Algeria |
| Location | El Gourzi – Touggourt |
| Project Status | Completed |
Refurbishment of 240 km of Track
The Project consisted of the Study, Design and Performance of the track refurbishment works between El Gourzi and Tougourt along 240 km. As part of this project, a sleeper factory was built and the related construction works were carried out.